Coordinate the Sandringham bar front installation
You are the assistant to the Installation Coordinator.
What has happened
Bayside Hospitality Group has ordered a curved oak veneer bar front with brass inlay for its Sandringham venue (JO-26-1047), installing from 14 October on a builder's site with a mezzanine. The builder locks the program on 2 October and needs Craftline's safe work method statement, crew induction records and delivery plan before then. The bar front is being built in the cabinet factory in three sections and needs the large truck and a crane or lift for the mezzanine. Jarrah Thompson has asked you to own the coordination and the installation schedule entry, and to flag anything that could slip the date, including the CNC service on 12 and 13 October.
Deliverables
- Site requirements record in the job order
- Safe work method statement
- Installation schedule entries for the three days
- Crew induction status list
- Coordination plan with risks
Documents to use
Systems to use
Installation and Delivery Schedule
Schedules crews and trucks to sites, records site induction and job safety analysis completion and captures handover and call-back status.
Job Order Register
Tracks every job from confirmed order through production, dispatch and installation to handover, with the job pack details and current status.
Plant and Machinery Register
Lists every machine, lifting device and vehicle with its risk assessment date, service schedule, status and authorised operators.
WHS Incident and Hazard Register
Records every injury, near miss, hazard and property damage report, the investigation and the corrective actions to closure.
Units of competency
Current on training.gov.au for the Furnishing Training Package as at 10 September 2026.
MSFFT4013Coordinate onsite installation of cabinetryMSFFM3041Determine and document requirements for cabinetry installationMSFWHS301Identify installation work hazards and select risk control strategiesMSFGN4001Research and meet ethical and compliance requirementsQualifications
MSF40222Certificate IV in Furniture Design and ManufacturingWhat to look for
Evidence guide
The safe work method statement must address the actual high risk work on this site with controls the crew can follow. Look for confirmed facts from the builder rather than assumptions, a schedule entry that matches the production capacity, an honest assessment of the CNC service clash, and a coordination plan that a manager could act on.